KNPC - CLEAN FUELS PROJECT , MAB1 PACKAGE – SHUAIBA OIL PIER|MECHANICAL, PIPING, PAINTING, ELECTRICAL AND INSTRUMENTATION , FOC LAYING, LLI, TANK MODIFICATION ETC.

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / PETROFAC (PSC JV)

Duration : JUN 14 - JUL 24

Status : Completed

KOC -JURASSIC PRODUCTION FACILITY (JPF 5)|AG PLANT PIPING TOTAL - GTU, SRU + OTHERS : FABRICATION & ERECTION, VALVE ERECTION, PAINTING, PIPE SUPPORT – PRIMARY & SECONDARY - SUPPLY & FABRICATION, INSULATION, PRE-COMMISSIONING WORKS

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KOC / JEREH

Duration : DEC 22 - JUL 24

Status : Completed

KIPIC - NEW REFINERY PROJECT (NRP) AL ZOUR PACKAGE - PKG #04 (SE J/V)|SUPPLY, FABRICATION & ERECTION OF STRUCTURAL HANDRAIL WORKS, MECHANICAL WORKS.

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / SAIPEM / ESSAR JV

Duration : MAR 20 - JAN 24

Status : Completed

KOC - GATHERING CENTRE GC-32|MECHANICAL – RESOURCE SUPPLY WORKS

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KOC / PETROFAC

Duration : APR 23 - DEC 23

Status : Completed

KIPIC - KLNG / AL ZOUR LNG IMPORT PROJECT|OFFSITE CONSTRUCTION WORK PACKAGE 02 – SMP WORKS. (STEEL STRUCTURE, MECHANICAL & PIPING WORKS)

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / HEC (HHK J/V)

Duration : JAN 18 - DEC 23

Status : Completed

KIPIC - NEW REFINERY PROJECT (NRP) AL ZOUR PACKAGE - PKG 5|PILE COATING & SCAFFOLDING WORKS

Scope of Work : Painting | Coating

Owner / Client : KIPIC / HDEC (HSS JV)

Duration : APR 23 - NOV 23

Status : Completed

KOC – NEW DESALTER TRAIN AT GC’S 09, 10, 19 & 21, SEK|FIELD PIPING ERECTION WORKS AT GC 19

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KOC / ALKHORAYEF

Duration : APR 20 - NOV 23

Status : Completed

KNPC - EPC & COMMISSIONING OF DEBOTTLENECKING OF COKER UNIT (U-20) MAB|DEMOLITION AND INSTALLATION OF TRAIN-1 SHUTDOWN WORKS – MECHANICAL, STRUCTURAL, PIPING

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / GULF SPIC

Duration : SEP 22 - NOV 22

Status : Completed

KNPC - CA/CPC/0442- PROCUREMENT AND CONSTRUCTION OF STATIC MIXERS FOR NLTF FACILITIES, MAA REFINERY|SUPPLY, FABRICATION, ERECTION, TESTING, PRE- COMMISSIONING OF STATIC MIXER AND ASSOCIATED PIPING

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / KNPC

Duration : JUN 21 - SEP 22

Status : Completed

KOC - GATHERING CENTRE GC-32|ABOVE GROUND PIPING, STEEL STRUCTURE ERECTION AND ASSOCIATED WORKS, RESOURCE SUPPLY

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KOC / SINOPEC TENTH

Duration : DEC 18 - AUG 22

Status : Completed

KOC - HEAVY OIL PRODUCTION FACILITY (HOPF) AT UMM NIQA|PLANT SHUTDOWN WORKS

Scope of Work : Maintenance | Turn Around

Owner / Client : KOC / SCHLUMBERGER

Duration : JAN 21 - APR 22

Status : Completed

KIPIC –NEW REFINERY PROJECT (NRP) AL ZOUR PACKAGE - PKG # 04 (SPES J/V)|TANK PAINTING WORKS (12 NO’S)

Scope of Work : Painting | Coating

Owner / Client : KIPIC / ESSAR LTD

Duration : NOV 19 - JUN 22

Status : Completed