KNPC - CB/CMS/2023|MAINTENANCE AND REPAIR OF 30 NOS OVERDUE TANKS AT MAB

Scope of Work : Maintenance | Turn Around

Owner / Client : KNPC / KNPC

Duration : JUN 23 - DEC 25

Status : Ongoing

KNPC - CA/CPC/0637|PCC FOR REROUTING OF NEUTRALIZATION PIT WATER FROM BOILER AREA TO NEW AGRP WASTE WATER SYSTEM AT MAA (UNIT-29& 35)

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / KNPC

Duration : APR 24 - OCT 25

Status : Ongoing

KAFCO - 22/23-33|REHABILITATION OF TANKS AND INSTALLATION OF ELECTROMECHANICAL ITEMS AT OLD DEPOT - 3 NOS

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KAFCO / KAFCO

Duration : FEB 24 - FEB 25

Status : Ongoing

KAFCO - 23/24-11|8 INCH ATK PIPELINE REHABILITATION WORK

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KAFCO / KAFCO

Duration : JUN 24 - JAN 25

Status : Ongoing

KNPC - CA/CPD/0263, REPLACEMENT OF ELEVATORS IN MAA|PIPING, ELECTRICAL & INSTRUMENTATION CONSTRUCTION PART A

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / AGECO

Duration : JUL 24 - DEC 24

Status : Ongoing

KAFCO - 24/25-07|MODIFICATION OF HYDRANT PITS IN NEW CARGO CITY

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KAFCO / KAFCO

Duration : SEP 24 - DEC 24

Status : Ongoing

KOC - JPF 1, JPF 2|MANPOWER SUPPLY, MISC. PIPING FABRICATION WORKS, SHUTDOWN / TURNAROUND MAINTENANCE WORKS

Scope of Work : Maintenance | Turn Around

Owner / Client : KOC / SCHLUMBERGER

Duration : JAN 20 - DEC 24

Status : Ongoing

KIPIC –NRP AL ZOUR PKG #01 (TSH J/V)|PRESERVATION AND COMMISSIONING ASSISTANCE

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / TECNICAS

Duration : AUG 17 - DEC 24

Status : Ongoing

KNPC - MAA, GAS TRAIN # 5, 502-S & 505-N EMPLACEMENT WORKS|MECHANICAL, PIPING INSTALLATION & ASSOCIATED WORKS, TOWER INTERNAL ERECTION, INSULATION, PRECOMMISSIONING ASST. MANPOWER SUPPLY

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / TECNICAS

Duration : SEP 16 - DEC 24

Status : Ongoing

KNPC - CLEAN FUELS PROJECT , MAB1 PACKAGE – SHUAIBA OIL PIER|MECHANICAL, PIPING, PAINTING, ELECTRICAL AND INSTRUMENTATION , FOC LAYING, LLI, TANK MODIFICATION ETC.

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / PETROFAC (PSC JV)

Duration : JUN 14 - JUL 24

Status : Completed

KNPC- CLEAN FUELS PROJECT (MAA)|W/M MANPOWER SUPPLY (INCLUDING LLI EQUIPMENT'S INSPECTION, PAINTING & OTHER WORKS), PRECOMMISSIONING ASST.

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / JGSK J/V

Duration : JUN 14 - NOV 24

Status : Ongoing

KNPC - CA/CPC/0543|PROCUREMENT, CONSTRUCTION AND COMMISSIONING FOR UPGRADING OFFSITE CHEMICAL DOSING FACILITY AT UNIT-61 IN MAA

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / KNPC

Duration : NOV 22 - NOV 24

Status : Ongoing