New Refinery Project I DBB Valve Installation & Resources Supply for Preservation works
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KIPIC / TSH jv-Tecnicas Reunidas
Duration : Dec 20 - Dec 21
Status : Ongoing
|
Desalter Project I Shop Piping Fabrication & External Painting of Piping Spools
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KOC / Alkhorayef
Duration : Dec 20 - Jun 21
Status : Ongoing
|
SKEC I UAE "M" Project I Manpower Mobilization
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : ADNOC / SK E&C
Duration : Jan 20 - May 21
Status : Completed
|
KIPIC-NRP-Pkg # 4 |Fabrication | Essar (SPES Jv)
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KIPIC / Essar (SPES Jv)
Duration : Mar 20 - Nov 20
Status : Completed
|
KIPIC-NRP-Pkg # 4 |Field joint & support painting works | Saipem (SPES Jv)
Scope of Work : Painting | Coating
Owner / Client : KIPIC / Saipem (SPES Jv)
Duration : Feb 20 - Sep 20
Status : Completed
|
KIPIC-NRP-Pkg # 4 |Fire Proofing | Saipem (SPES Jv)
Scope of Work : Painting | Coating
Owner / Client : KIPIC / Saipem (SPES Jv)
Duration : Mar 20 - Apr 21
Status : Completed
|
KIPIC-NRP-Pkg #4|Tankage Painting | Essar (SPES Jv)
Scope of Work : Painting | Coating
Owner / Client : KIPIC / Essar (SPES Jv)
Duration : Nov 19 - Sep 20
Status : Ongoing
|
KAFCO-Rehabilitation of Tanks 4,5&6 | Rebottoming | Painting | Cathodic Protection | Civil & associated
Scope of Work : Painting | Coating
Owner / Client : KAFCO / KAFCO
Duration : May 19 - Mar 21
Status : Completed
|
KOC - GC 32 | Steel Structure Erection
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KOC / SINOPEC TENTH
Duration : Dec 18 - Oct 21
Status : Ongoing
|
KIPIC-NRP-Pkg # 1|Steam Tracing (Crude & ARDS)
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KIPIC / TSH jv- TECNICAS REUNIDAS
Duration : Apr 18 - Sep 19
Status : Completed
|
KIPIC-NRP-Pkg # 01- A&B | Erection of Fired Heaters
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KIPIC / TSH jv- TECNICAS REUNIDAS
Duration : Sep 17 - Mar 19
Status : Completed
|
KIPIC-NRP-Pkg # 1 | Steel Structure Erection
Scope of Work : Mechanical | Steel Structure | Piping
Owner / Client : KIPIC / TSH jv - SINOPEC FIFTH
Duration : Jan 17 - Jun 19
Status : Completed
|