SKEC I UAE "M" Project I Manpower Mobilization

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : ADNOC / SK E&C

Duration : Jan 20 - May 21

Status : Completed

KIPIC-NRP-Pkg # 4 |Fabrication | Essar (SPES Jv)

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / Essar (SPES Jv)

Duration : Mar 20 - Nov 20

Status : Completed

KIPIC-NRP-Pkg # 1|Steam Tracing (Crude & ARDS)

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / TSH jv- TECNICAS REUNIDAS

Duration : Apr 18 - Sep 19

Status : Completed

KIPIC-NRP-Pkg # 01- A&B | Erection of Fired Heaters

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / TSH jv- TECNICAS REUNIDAS

Duration : Sep 17 - Mar 19

Status : Completed

KIPIC-NRP-Pkg # 1 | Steel Structure Erection

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / TSH jv - SINOPEC FIFTH

Duration : Jan 17 - Jun 19

Status : Completed

KOC-JPF-JURASSIC PRODUCTION FACILITY | Piping Pre-Fabrication, Erection.

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KOC / SCHLUMBERGER - SLB

Duration : Jul 17 - Oct 19

Status : Completed

KIPIC-NRP-Pkg # 5 | Onshore Pipeline | HSS

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / HSS jv- SK E&C

Duration : Sep 17 - Sep 18

Status : Completed

KIPIC-NRP-Pkg # 1 | Steel Structure & Erection

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / TSH jv - TECNICAS REUNIDAS

Duration : Oct 17 - Dec 19

Status : Completed

Al-Zour Refinery - Package # 01 | Heavy Lifting Assistance Works

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KIPIC / TSH jv - SINOPEC FIFTH

Duration : Nov 16 - Apr 17

Status : Completed

CFP MAB Package #01 - Shuaiba Refinery | Civil and Equipment Demolition Works

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KNPC / Consolidated Contractors Company W.L.L. (CCC)

Duration : Oct 15 - Apr 18

Status : Completed

Sabiya CCGT Project (HHI) and KOC’s BS projects (Petrofac)

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : Ministry of Electricity and Water (MEW) / Sayed Hamid Behbehani & Sons Co. (SHBC)

Duration : 2009 - 2010

Status : Completed

Wara Pressure Maintenance Project

Scope of Work : Mechanical | Steel Structure | Piping

Owner / Client : KOC / GS E&C

Duration : Mar 14 - Apr 18

Status : Completed