KIPIC-NRP-Pkg # 4 |Field joint & support painting works | Saipem (SPES Jv)
Scope of Work : Painting | Coating
Owner / Client : KIPIC / Saipem (SPES Jv)
Duration : Feb 20 - Sep 20
Status : Completed
|
KIPIC-NRP-Pkg # 4 |Fire Proofing | Saipem (SPES Jv)
Scope of Work : Painting | Coating
Owner / Client : KIPIC / Saipem (SPES Jv)
Duration : Mar 20 - Apr 21
Status : Completed
|
KAFCO-Rehabilitation of Tanks 4,5&6 | Rebottoming | Painting | Cathodic Protection | Civil & associated
Scope of Work : Painting | Coating
Owner / Client : KAFCO / KAFCO
Duration : May 19 - Mar 21
Status : Completed
|
Sabiya New CCGT Project
Scope of Work : Painting | Coating
Owner / Client : Ministry of Electricity and Water (MEW) / FISIA ITALIMPIANTI
Duration : Mar 11 - Jun 12
Status : Completed
|
MAA SHFP - Sulphur Handling Facilities | Painting Works & Painting Man Power Supply,
Scope of Work : Painting | Coating
Owner / Client : KNPC / DAELIM
Duration : Nov 14 - Feb 20
Status : Completed
|
MAA Refinery | FCC Revamp Project
Scope of Work : Painting | Coating
Owner / Client : KNPC / DAELIM
Duration : Apr 15 - Jan 17
Status : Completed
|
Sabiya New CCGT Project | Blasting & Painting Works
Scope of Work : Painting | Coating
Owner / Client : Ministry of Electricity and Water (MEW) / Hyundai Heavy Industries (HHI)
Duration : 2010 - 2011
Status : Completed
|
LOCAL MARKETING - LM | Expansion and Revamping of Ahamdi Deport.
Scope of Work : Painting | Coating
Owner / Client : KNPC / PUNJ LLOYD
Duration : May 15 - Dec 19
Status : Completed
|
MAA Refinery - LPG Train 4 | Blasting & Painting works
Scope of Work : Painting | Coating
Owner / Client : KNPC / DAELIM
Duration : Jan 12 - Sep 15
Status : Completed
|